Mission Operations Days: 2004/311 to 2004/317
November 06, 2004 00:00:00 GMT to November 12, 2004 00:00:00 GMT
Aqua Spacecraft and MODIS Instrument Status:
PM-1 "Aqua" is in Fine Pointing Normal Mode FM1 MODIS is in B-Side Nominal Science Mode |
||
---|---|---|
Component | State(s) | Comment |
Blackbody | A Off; B On (285K) | Nominal Science Mode |
Calibration Electronics | A Off; B On | Nominal Science Mode |
Control Processor | A Off; B On | Nominal Science Mode |
Nadir Door | Unlatched, Open | Nominal Science Mode |
Space View Door | Unlatched, Open | Nominal Science Mode |
Solar Diffuser Door | Unlatched, Closed | Nominal Science Mode |
FDDI Formatter | A Off; B On | Nominal Science Mode |
FDDI Port | A Off; B On | Nominal Science Mode |
FIFO Memory | #1 & #2 Off; #3 & #4 On | Nominal Science Mode |
Format Processor | A Off; B On | Nominal Science Mode |
Power Supplies | #1 Off, #2 On | Nominal Science Mode |
PV VIS FPA | A Off; B On | Nominal Science Mode |
PV NIR FPA | A Off; B On | Nominal Science Mode |
PV SMIR FPA | A Off; B On | Nominal Science Mode |
PV LWIR FPA | A Off; B On | Nominal Science Mode |
PC LWIR FPA | A Off; B On | Nominal Science Mode |
RC Outgas Heaters | All 3 (CS, IS, OS) Off | Nominal Science Mode |
RC LWIR FPA Heater | Off | Nominal Science Mode |
RC SMIR FPA Heater | On (83K) | Nominal Science Mode |
Scan Assembly | A Off; B On | Nominal Science Mode |
SDSM | Off | Nominal Science Mode |
SRCA | Off | Nominal Science Mode |
PS1 Survival Heaters | Enabled | Nominal Science Mode |
PS2 Survival Heaters | Enabled | Nominal Science Mode |
Timing Generator | A Off; B On | Nominal Science Mode |
Flight Software | Rev BJ + 1 set of patches
|
Nominal Science Mode |
Inhibit Ids Set | None | Nominal Science Mode |
This Week’s Completed MODIS Activities:
Saturday, November 6, 2004
None
Sunday, November 7, 2004
None
Monday, November 8, 2004
None
Tuesday, November 9, 2004
None
Wednesday, November 10, 2004
None
Thursday, November 11, 2004
None
Friday, November 12, 2004
None
This Week’s Scheduled MODIS Activities Not Completed:
None
Upcoming MODIS Events:
Calibrations for November include biweekly SDSM, monthly SRCA Full Radiometric, and bimonthly SRCA Full Spatial calibrations.
Monday, November 15, 2004
2004/320 20:50:45-21:04:43 MCL MOD_OA16_SDSM_SCREEN.2 OA-16: SD/SDSM Screened - B-Side
2004/320 22:29:37-22:29:39 MCL MOD_OA15_SDSM_OPEN.1 OA-15: SD/SDSM Open - B-Side
2004/320 23:15:00-23:15:16 MCL MOD_SRCA_SETUP_NO_L2.2 SRCA setup activity using lamp #4 in lieu of lamp #2
2004/320 23:22:03-23:56:16 MCL MOD_OA19_SRCA_FULL_RAD.1 OA-19: SRCA Full Radiometric Calibration - B Side
Data Collect from 23:37:57-23:56:15
Maneuvers:
The next Aqua MODIS Lunar Calibration Roll will be on DOY 2004/327 (November 22, 2004). The roll angle will be –4.1991 degrees for a nominal 6:30 (390 second) collection.
No official date has yet been scheduled for the Aqua Deep Space Calibration pitch maneuver(s).
MODIS Anomalies:
None
General Instrument Comments:
FM1 MODIS is in Science Mode. The SVD and NAD are Open, the survival heaters are enabled, and the Black Body is heated to 285 K.
MODIS Telemetry Trends:
The FM1 MODIS instrument telemetry is trending nominally.
Non-MODIS Significant Events:
The EMOS mission status webpage (which includes instrument data loss records) can be found at the following URL. Note that a password is now required to access the EOS mission links webpages. There are directions at the URL below for how to obtain a username/password.
http://jupiter02.gsfc.nasa.gov/links/links.htm
Limited Life Item Status:
SRCA 10W Lamp #1: 238.8 of 500 hours
SRCA 10W Lamp #2: 184.3 of 500 hours
SRCA 10W Lamp #3: 201.1 of 500 hours
SRCA 10W Lamp #4: 74.3 of 500 hours
SRCA 1W Lamp #1: 508.4 of 5000 hours
SRCA 1W Lamp #2: 269.8 of 5000 hours
Solar Diffuser Door: 2278 of 3022 Movements
Nadir Aperture Door: 1053 of 1316 Movements
Space View Door: 632 of 1316 Movements